Notice of Final Federal Agency Actions on Proposed Highway Projects in Texas

Michael T. Leary
Federal Highway Administration
18 April 2019


[Federal Register Volume 84, Number 75 (Thursday, April 18, 2019)]
[Notices]
[Pages 16316-16320]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-07178]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Highway Administration


Notice of Final Federal Agency Actions on Proposed Highway 
Projects in Texas

AGENCY: Texas Department of Transportation (TxDOT), Federal Highway 
Administration (FHWA), U.S. Department of Transportation.

ACTION: Notice of limitation on claims for judicial review of actions 
by TxDOT and Federal agencies.

-----------------------------------------------------------------------

SUMMARY: This notice announces actions taken by TxDOT and Federal 
agencies that are final. The environmental review, consultation, and 
other actions required by applicable Federal environmental laws for 
these projects are being, or have been, carried-out by TxDOT pursuant 
to an assignment agreement executed by FHWA and TxDOT. The actions 
relate to various proposed highway projects in the State of Texas. 
These actions grant licenses, permits, and approvals for the projects.

DATES: By this notice, TxDOT is advising the public of final agency 
actions subject to 23 U.S.C. 139(l)(1). A claim seeking judicial review 
of TxDOT and Federal agency actions on the highway projects will be 
barred unless the claim is filed on or before the deadline. For the 
projects listed below, the deadline is September 15, 2019. If the 
Federal law that authorizes judicial review of a claim provides a time 
period of less than 150 days for filing such a claim, then that shorter 
time period still applies.

FOR FURTHER INFORMATION CONTACT: Carlos Swonke, Environmental Affairs 
Division, Texas Department of Transportation, 125 East 11th Street, 
Austin, Texas 78701; telephone: (512)

[[Page 16317]]

416-2734; email: carlos.swonke@txdot.gov. TxDOT's normal business hours 
are 8:00 a.m.-5:00 p.m. (central time), Monday through Friday.

SUPPLEMENTARY INFORMATION: The environmental review, consultation, and 
other actions required by applicable Federal environmental laws for 
these projects are being, or have been, carried-out by TxDOT pursuant 
to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 
2014, and executed by FHWA and TxDOT.
    Notice is hereby given that TxDOT and Federal agencies have taken 
final agency actions by issuing licenses, permits, and approvals for 
the highway projects in the State of Texas that are listed below.
    The actions by TxDOT and Federal agencies and the laws under which 
such actions were taken are described in the Categorical Exclusion 
(CE), Environmental Assessment (EA), or Environmental Impact Statement 
(EIS) issued in connection with the projects and in other key project 
documents. The CE, EA, or EIS and other key documents for the listed 
projects are available by contacting TxDOT at the address provided 
above.
    This notice applies to all TxDOT and Federal agency decisions as of 
the issuance date of this notice and all laws under which such actions 
were taken, including but not limited to:
    1. General: National Environmental Policy Act (NEPA) [42 U.S.C. 
4321-4351]; Federal-Aid Highway Act [23 U.S.C. 109].
    2. Air: Clean Air Act, 42 U.S.C. 7401-7671(q).
    3. Land: Section 4(f) of the Department of Transportation Act of 
1966 [49 U.S.C. 303]; Landscaping and Scenic Enhancement (Wildflowers), 
23 U.S.C. 319.
    4. Wildlife: Endangered Species Act [16 U.S.C. 1531-1544 and 
Section 1536], Marine Mammal Protection Act [16 U.S.C. 1361], Fish and 
Wildlife Coordination Act [16 U.S.C. 661-667(d)], Migratory Bird Treaty 
Act [16 U.S.C. 703-712].
    5. Historic and Cultural Resources: Section 106 of the National 
Historic Preservation Act of 1966, as amended [54 U.S.C. 300101 et 
seq.]; Archeological Resources Protection Act of 1977 [16 U.S.C. 
470(aa)-11]; Archeological and Historic Preservation Act [54 U.S.C. 
312501 et seq.]; Native American Grave Protection and Repatriation Act 
(NAGPRA) [25 U.S.C. 3001-3013].
    6. Social and Economic: Civil Rights Act of 1964 [42 U.S.C. 
2000(d)-2000(d)(1)]; American Indian Religious Freedom Act [42 U.S.C. 
1996]; Farmland Protection Policy Act (FPPA) [7 U.S.C. 4201-4209].
    7. Wetlands and Water Resources: Clean Water Act, 33 U.S.C. 1251-
1377 (Section 404, Section 401, Section 319); Land and Water 
Conservation Fund (LWCF), 16 U.S.C. 4601-4604; Safe Drinking Water Act 
(SDWA), 42 U.S.C. 300(f)-300(j)(6); Rivers and Harbors Act of 1899, 33 
U.S.C. 401-406; Wild and Scenic Rivers Act, 16 U.S.C. 1271-1287; 
Emergency Wetlands Resources Act, 16 U.S.C. 3921, 3931; TEA-21 Wetlands 
Mitigation, 23 U.S.C. 103(b)(6)(m), 133(b)(11); Flood Disaster 
Protection Act, 42 U.S.C. 4001-4128.
    8. Executive Orders: E.O. 11990 Protection of Wetlands; E.O. 11988 
Floodplain Management; E.O. 12898, Federal Actions to Address 
Environmental Justice in Minority Populations and Low Income 
Populations; E.O. 11593 Protection and Enhancement of Cultural 
Resources; E.O. 13007 Indian Sacred Sites; E.O. 13287 Preserve America; 
E.O. 13175 Consultation and Coordination with Indian Tribal 
Governments; E.O. 11514 Protection and Enhancement of Environmental 
Quality; E.O. 13112 Invasive Species. (Catalog of Federal Domestic 
Assistance Program Number 20.205, Highway Planning and Construction.)
    The projects subject to this notice are:
    1. SH 289 from North of Business 289C to North of CR 60/CR 107 in 
Collin County, Texas. The proposed project would reconstruct and widen 
the roadway from a two-lane undivided roadway to an urban four-lane 
divided highway. The proposed improvements would consist of one 12-foot 
travel lane and one 14-foot outside shared-use lane in each direction, 
and a 42-foot raised center median. The length of the proposed project 
is approximately 2.56 miles. The purpose of the proposed project is to 
improve mobility and traffic operations for existing and future traffic 
demand in the project area. The actions by TxDOT and Federal agencies 
and the laws under which such actions were taken are described in, the 
Categorical Exclusion Determination issued on December 18, 2018, and 
other documents in the TxDOT project file. The Categorical Exclusion 
Determination and other documents in the TxDOT project file are 
available by contacting TxDOT at the address provided above or the 
TxDOT Dallas District Office at 4777 E Highway 80, Mesquite, TX 75150; 
telephone (214) 320-4480.
    2. IH 45 Central Walker County Project Segment 2A, from 0.3 miles 
north of SH 19 to 0.9 miles north of SH 30 in Walker County, Texas. The 
proposed project would replace existing main-lane pavement with new 
pavement and widen to six travel-lanes (three north and three south), 
from four travel lanes, currently, (two north and two south). The main-
lane widening would be accomplished by adding additional lanes to the 
inside of the existing main-lanes. The project also includes adding 
collector-distributor roads, which are roads that parallel and connect 
the main travel lanes and frontage roads. The proposed improvements are 
needed to bring the interstate facility up to current standards for 
design and safety to increase capacity in order to meet future traffic 
volumes. The purpose of the project is to enhance freight mobility and 
address congestion along the IH 45 corridor. The actions by TxDOT and 
Federal agencies and the laws under which such actions were taken are 
described in the Open-ended (d) CE classification letter approved on 
January 04, 2019, and other related documents can be found in the TxDOT 
project file. The Categorical Exclusion Determination and other 
documents in the TxDOT project file are available by contacting TxDOT 
at the address provided above or the TxDOT Bryan District Office at 
2591 North Earl Rudder Freeway, Bryan, Texas 77803; telephone (979) 
778-9764.
    3. US 59 from FM 2021 to 0.34 miles north of US 59/SL 287, Angelina 
County, Texas. The purpose of the proposed project is to upgrade US 59 
to meet interstate standards by providing two-lane north and south 
bound frontage roads from FM 2021 to 0.34 miles north of US 59 and Loop 
287 near Redland, Texas. The proposed project also includes sidewalks 
and reconstruction of main lanes with flush median. The proposed 
project is 2.45 miles in length. The actions by TxDOT and Federal 
agencies and the laws under which such actions were taken are described 
in the Categorical Exclusion approved on July 31, 2018, and the 
Amendment to Categorical Exclusion Determination issued on January 14, 
2019, and other documents in the TxDOT project file. The Categorical 
Exclusion Determination and other documents in the TxDOT project file 
are available by contacting TxDOT at the address provided above or the 
TxDOT Lufkin District Office at 1805 North Timberland Drive, Lufkin, TX 
75901; telephone (936) 633-4395.
    4. County Road (CR) 101 (Bailey Road) from CR 90 to Farm-to-Market 
Road (FM) 1128 (Manvel Road) in Brazoria County, Texas. The 2.2 mile 
project will widen CR 101 to a four-lane divided boulevard with raised 
median,

[[Page 16318]]

left-turn bays, a sidewalk, curb-and-gutter drainage and a detention 
pond. The actions by TxDOT and Federal agencies and the laws under 
which such actions were taken are described in the Categorical 
Exclusion Determination approved January 25, 2019 and other documents 
in the TxDOT project file. The Categorical Exclusion Determination and 
other documents in the TxDOT project file are available by contacting 
TxDOT at the address provided above or the TxDOT Houston District 
Office located at 7600 Washington Avenue, Houston, Texas 77007; 
telephone (713) 802-5076.
    5. IH 35 from South of Lakeway Drive to South of Williams Drive, 
Williamson County, Texas. The project includes reconstructing the 
existing IH 35 at Williams Drive interchange, modifying the frontage 
roads, constructing collector/distributor roads and a shared use path. 
The project is approximately 2 miles in length. The actions by TxDOT 
and Federal agencies and the laws under which such actions were taken 
are described in the Categorical Exclusion Determination issued on 
January 25, 2019 and other documents in the TxDOT project file. The 
Categorical Exclusion Determination and other documents in the TxDOT 
project file are available by contacting TxDOT at the address provided 
above or the TxDOT Austin District Office at 7901 North I-35, Austin, 
TX 78753; telephone (512) 832-7000.
    6. SH 71 from FM 2765 to FM 1300 in Wharton County, Texas. The 
proposed project would construct a center left turn lane and add an 
additional travel lane in each direction from FM 2765 to FM 1300 for a 
length of 1.643 miles. The purpose of the project is to improve safety 
and mobility. The actions by TxDOT and Federal agencies and the laws 
under which such actions were taken are described in the Categorical 
Exclusion Determination issued on February 4, 2019 and other documents 
in the TxDOT project file. The Categorical Exclusion Determination and 
other documents in the TxDOT project file are available by contacting 
TxDOT at the address provided above or the TxDOT Yoakum District Office 
at 403 Huck St., Yoakum, TX 77995; telephone (361) 293-4436.
    7. US 87 at Guadalupe River in DeWitt County, Texas. The proposed 
project would construct a new bridge parallel to the existing bridge to 
create a one-way pair structure over the Guadalupe River. The project 
would also realign the intersection of US 87 and US 183 at the south 
end of the project. The length of the project is 1.212 miles. The 
purpose of the project is to construct a new bridge that meets current 
design and safety standards. The actions by TxDOT and Federal agencies 
and the laws under which such actions were taken are described in the 
Categorical Exclusion Determination issued on February 4, 2019 and 
other documents in the TxDOT project file. The Categorical Exclusion 
Determination and other documents in the TxDOT project file are 
available by contacting TxDOT at the address provided above or the 
TxDOT Yoakum District Office at 403 Huck St., Yoakum, TX 77995; 
telephone (361) 293-4436.
    8. US 90 over the Colorado River in Colorado County, Texas. The 
proposed project would construct a new bridge parallel to the existing 
bridge to create a one-way pair structure over the Colorado River. The 
length of the project is 0.364 mile. The purpose of the project is to 
construct a new bridge that meets current design and safety standards. 
The actions by TxDOT and Federal agencies and the laws under which such 
actions were taken are described in the Categorical Exclusion 
Determination issued on February 7, 2019 and other documents in the 
TxDOT project file. The Categorical Exclusion Determination and other 
documents in the TxDOT project file are available by contacting TxDOT 
at the address provided above or the TxDOT Yoakum District Office at 
403 Huck St., Yoakum, TX 77995; telephone (361) 293-4436.
    9. Red Bluff Road from Kirby Boulevard to State Highway 146, in 
Harris County, Texas. The 1.5 mile project will construct two new 
eastbound lanes and convert the existing roadway to westbound lanes, 
separated by a raised median. The project will also include the 
addition of a two-lane eastbound bridge (with a 10-foot-wide shared-use 
trail) parallel to the existing Taylor Lake Bridge. The existing 
undivided two-lane bridge will be improved to facilitate two lanes of 
westbound traffic and a wide shoulder lane. The actions by TxDOT and 
Federal agencies and the laws under which such actions were taken are 
described in the Categorical Exclusion Determination approved February 
19, 2019 and other documents in the TxDOT project file. The Categorical 
Exclusion Determination and other documents in the TxDOT project file 
are available by contacting TxDOT at the address provided above or the 
TxDOT Houston District Office located at 7600 Washington Avenue, 
Houston, Texas 77007; telephone (713) 802-5076.
    10. Farm-to-Market (FM) 521 from FM 2234 to State Highway (SH) 6 in 
Fort Bend County, Texas. The 5.3 mile project will reconstruct and 
widen the FM 521 roadway from a two-lane undivided roadway to a four-
lane divided roadway. The project also includes raised medians, a grade 
separation over FM 521 at Broadway Street, and a sidewalk on the east 
side of the roadway, intersection improvements, and turn lanes at 
various locations. The actions by TxDOT and Federal agencies and the 
laws under which such actions were taken are described in the 
Categorical Exclusion Determination approved February 19, 2019 and 
other documents in the TxDOT project file. The Categorical Exclusion 
Determination and other documents in the TxDOT project file are 
available by contacting TxDOT at the address provided above or the 
TxDOT Houston District Office located at 7600 Washington Avenue, 
Houston, Texas 77007; telephone (713) 802-5076.
    11. FM 1516 from IH 10 East to FM 78, Bexar County, Texas. The 
project includes widening the roadway from two lanes to four lanes with 
a center turn lane. Sidewalks and bike lanes are also included with the 
project. The project is approximately 3.7 miles in length. The actions 
by TxDOT and Federal agencies and the laws under which such actions 
were taken are described in the Categorical Exclusion Determination 
issued on February 21, 2019 and other documents in the TxDOT project 
file. The Categorical Exclusion Determination and other documents in 
the TxDOT project file are available by contacting TxDOT at the address 
provided above or the TxDOT San Antonio District Office at 4615 NW Loop 
410, San Antonio, TX 78229; telephone (210) 615-5839.
    12. US 175 from FM 148 to CR 4106 in Kaufman County, Texas. The 
proposed project would entail the construction of a new frontage road 
on the south side of US 175. The existing two-way frontage road on the 
north side of US 175 would be changed to one-way operation. The length 
of the proposed project is approximately 2.8 miles. The purpose of the 
proposed project is to improve the safety, mobility and access along 
the south side of US 175 and to accommodate future traffic demand in 
the area. The actions by TxDOT and Federal agencies and the laws under 
which such actions were taken are described in the documentation 
supporting the Categorical Exclusion (CE) Determination approved on 
February 22, 2019, and other documents in the TxDOT project file. The 
CE Determination and other documents are available by contacting TxDOT 
at the address provided above or the TxDOT

[[Page 16319]]

Dallas District Office at 4777 E Highway 80, Mesquite, TX 75150; 
telephone: (214) 320-4480.
    13. FM 1518 from FM 78 to IH 10, Bexar County, Texas. The project 
includes widening the roadway from two lanes to four lanes with a 
raised median. A shared use path is also included with the project. The 
project is approximately 5.53 miles in length. The actions by TxDOT and 
Federal agencies and the laws under which such actions were taken are 
described in the Categorical Exclusion Determination issued on February 
25, 2019 and other documents in the TxDOT project file. The Categorical 
Exclusion Determination and other documents in the TxDOT project file 
are available by contacting TxDOT at the address provided above or the 
TxDOT San Antonio District Office at 4615 NW Loop 410, San Antonio, TX 
78229; telephone (210) 615-5839.
    14. Smith Ranch Road from Hughes Ranch Road to north of Broadway 
(FM 518) in Brazoria County, Texas. The 0.76 mile project will widen 
Smith Ranch Road to a four-lane, divided roadway. The project will also 
include curb-and-gutter drainage with an underground storm sewer 
system, a raised median and a 10-foot-wide path on the west side of the 
roadway to accommodate both pedestrians and bicyclists. The actions by 
TxDOT and Federal agencies and the laws under which such actions were 
taken are described in the Categorical Exclusion Determination approved 
February 26, 2019 and other documents in the TxDOT project file. The 
Categorical Exclusion Determination and other documents in the TxDOT 
project file are available by contacting TxDOT at the address provided 
above or the TxDOT Houston District Office located at 7600 Washington 
Avenue, Houston, Texas 77007; telephone (713) 802-5076.
    15. US 377 from South of FM 1171 to North of Crawford Road in 
Denton County, Texas. The proposed project would widen the proposed 
roadway from a two-lane rural roadway to a four-lane divided urban 
roadway that would consist of one 12-foot lane and one 14-foot lane in 
each direction with a 19-foot raised median. The proposed project would 
include dedicated left-turn lanes, signalized intersections, and six-
foot sidewalks on both sides of the roadway for the entire length of 
the project. The length of the proposed project is approximately 6.130 
miles. The purpose of the proposed project is to increase vehicle 
mobility and safety, decrease congestion and provide alternative modes 
of transportation within the project limits. The actions by TxDOT and 
Federal agencies and the laws under which such actions were taken are 
described in the documentation supporting the Categorical Exclusion 
(CE) Determination approved on March 13, 2019, and other documents in 
the TxDOT project file. The CE Determination and other documents are 
available by contacting TxDOT at the address provided above or the 
TxDOT Dallas District Office at 4777 E Highway 80, Mesquite, TX 75150; 
telephone: (214) 320-4480.
    16. Loop 375 (Purple Heart Memorial Highway) from Spur 601 (Liberty 
Expressway) to US 62/180 (Montana Avenue) in El Paso County, Texas. The 
proposed Loop 375 project would improve mobility and reduce congestion 
by widening Loop 375 from the existing four-lane facility to a six-lane 
facility (three lanes in each direction), with three-lane frontage 
roads on either side of Loop 375 and a hike and bike trail along the 
southbound Loop 375 frontage road, which would be constructed in the 
first phase. The proposed project would also provide improvements to 
the Loop 375 and Spur 601 intersections by constructing three direct 
connectors, which would be constructed in a subsequent phase(s). The 
length of the proposed project is approximately 5.3 miles along Loop 
375 and 0.1 mile along Spur 601. The actions by TxDOT and Federal 
agencies and the laws under which such actions were taken are described 
in the Final Environmental Assessment (EA) approved on January 18, 
2019, Finding of No Significant Impact (FONSI) issued on January 18, 
2019 and other documents in the TxDOT project file. The Environmental 
Assessment and other documents in the TxDOT project file are available 
by contacting TxDOT at the address provided above or the TxDOT El Paso 
District, 13301 Gateway West, El Paso, TX 79928; telephone (915) 790-
4340.
    17. FM 2514 from East of Lavon Parkway to Brown Street in Collin 
County, Texas. The proposed project would widen an existing two-lane 
roadway to a four-lane (ultimately six-lane) urban divided highway with 
a 14-foot outside shared-use lane and an 11-foot inside lane with a 40-
foot raised center median. The length of the proposed project is 
approximately 3.34 miles. The purpose of the proposed project is to 
reduce congestion and enhance safety. The actions by TxDOT and Federal 
agencies and the laws under which such actions were taken are described 
in the Final Environmental Assessment (EA) approved on February 5, 
2019, Finding of No Significant Impact (FONSI) issued on February 5, 
2019 and other documents in the TxDOT project file. The EA and other 
documents are available by contacting TxDOT at the address provided 
above or the TxDOT Dallas District Office at 4777 E Highway 80, 
Mesquite, TX 75150; telephone: (214) 320-4480.
    18. IH 30 from Bass Pro Drive to West of FM 2642 Dallas and 
Rockwall Counties, Texas. Beginning at Bass Pro to Horizon, the 
proposed improvements would widen this existing section of the roadway 
to accommodate adding shoulders along the existing four mainlanes 
(currently 3 lanes and one auxiliary lane in each direction). From 
Dalrock Road to SH 205, the proposed improvements would reconstruct and 
widen this section from six mainlanes (3 lanes in each direction) to 
eight mainlanes (4 lanes in each direction), and would reconstruct the 
four discontinuous frontage roads (2 lanes in each direction) to six-
lane continuous frontage roads (3 lanes in each direction), to include 
bicycle and pedestrian accommodations crossing Lake Ray Hubbard. From 
SH 205 to West of FM 2642 (Hunt County Line), the proposed improvements 
would reconstruct and widen this section from four mainlanes (2 lanes 
in each direction) to six mainlanes (3 lanes in each direction), and 
would reconstruct the existing four lane frontage roads (two lanes in 
each direction). Other improvements for this project include the 
reconstruction of interchanges at Horizon Road, FM 548, and FM 35, 
construction of new interchanges at Ben Payne Road/Rochelle Road, 
Blackland Road, and Floyd Road (future Outer Loop), and associated ramp 
modifications. The length of the proposed project is approximately 17 
miles. The purpose of the proposed project is to reduce traffic 
congestion and improve mobility along IH-30 within the project limits. 
The actions by TxDOT and Federal agencies and the laws under which such 
actions were taken are described in the Final Environmental Assessment 
(EA) approved on March 19, 2019, Finding of No Significant Impact 
(FONSI) issued on March 19, 2019 and other documents in the TxDOT 
project file. The EA and other documents are available by contacting 
TxDOT at the address provided above or the TxDOT Dallas District Office 
at 4777 E Highway 80, Mesquite, TX 75150; telephone: (214) 320-4480.
    19. FM 16 from 4 miles west of FM 849 (CR 481-E) to US 69 in 
Lindale, Smith County, Texas. The project includes the resurfacing of 
the existing roadway from 4 miles west of FM 849

[[Page 16320]]

(CR 481-E) to approximately 1250 ft. west of CR 479. After resurfacing, 
this section would be striped to accommodate two 12-ft.-wide lanes in 
each direction with 2-ft.-wide shoulders. No capacity would be added or 
other improvements made within this section. The roadway, between the 
resurfaced section and US 69, would be reconstructed as either three-
lanes or five-lanes, as described below. The length of the project, 
including all transitions, is approximately 4.4 miles. From 
approximately 1250 ft. west of CR 479 to approximately 500 ft. west of 
the intersection with CR 436, FM 16 would be reconstructed as a three-
lane rural highway. From west of CR 436 to the future intersection with 
Toll 49, FM 16 would be reconstructed as a five-lane rural highway. 
From Toll 49 to US 69, FM 16 would be reconstructed as a five-lane 
urban section. The actions by TxDOT and Federal agencies and the laws 
under which such actions were taken are described in the Final 
Environmental Assessment approved on March 8, 2019, the Finding of No 
Significant Impact issued on March 8, 2019, and other documents in the 
TxDOT project file. The EA, FONSI and other documents in the TxDOT 
project file are available by contacting TxDOT at the address provided 
above or the TxDOT Tyler District Office at 2709 W Front St., Tyler, TX 
75702; telephone (903) 510-9267.
    20. IH 35 from FM 3406 to RM 1431, Williamson County, Texas. The 
project includes widening the northbound frontage road, grading and 
improvements to drainage and driveway areas. The project is 
approximately 1.65 miles in length. The actions by TxDOT and Federal 
agencies and the laws under which such actions were taken are described 
in the Categorical Exclusion Determination issued on February 20, 2019 
and other documents in the TxDOT project file. The Categorical 
Exclusion Determination and other documents in the TxDOT project file 
are available by contacting TxDOT at the address provided above or the 
TxDOT Austin District Office at 7901 North I-35, Austin, TX 78753; 
telephone (512) 832-7000.
    21. Deck Plaza from Marsalis Avenue to Ewing Avenue in Dallas 
County, Texas. The proposed project proposes to construct a deck plaza 
over IH 35E from Marsalis Avenue to Ewing Avenue. The deck would be 
constructed to ultimately create an approximate 5.5 acre urban deck 
plaza sponsored by the City of Dallas. The purpose of the proposed 
project is to provide an enhancement to the community, encourage 
economic development opportunities in the area, and improve pedestrian 
and bicycle connectivity in the project area. The actions by TxDOT and 
Federal agencies and the laws under which such actions were taken are 
described in, the Categorical Exclusion Determination issued on July 
14, 2017, and other documents in the TxDOT project file. The 
Categorical Exclusion Determination and other documents in the TxDOT 
project file are available by contacting TxDOT at the address provided 
above or the TxDOT Dallas District Office at 4777 E Highway 80, 
Mesquite, TX 75150; telephone (214) 320-4480.
    22. US 67 from Belt Line Road to IH 20 in Dallas County, Texas. The 
proposed project would widen the roadway from a four-lane to a six-lane 
divided highway. The proposed roadway would include one additional 12-
foot travel lane with a 10-foot outside shoulder and four-foot inside 
shoulder in each direction. Proposed improvements would also include 
the addition of U-turn bridges at Belt Line Road and FM 1382. The 
length of the proposed project is approximately 5.7 miles. The purpose 
of the proposed project is to reduce traffic congestion and correct 
roadway deficiencies. The actions by TxDOT and Federal agencies and the 
laws under which such actions were taken are described in, the 
Categorical Exclusion Determination issued on February 3, 2017, and 
other documents in the TxDOT project file. The Categorical Exclusion 
Determination and other documents in the TxDOT project file are 
available by contacting TxDOT at the address provided above or the 
TxDOT Dallas District Office at 4777 E Highway 80, Mesquite, TX 75150; 
telephone (214) 320-4480.

    Authority: 23 U.S.C. 139(l)(1).

    Issued on: April 5, 2019.
Michael T. Leary,
Director, Planning and Program Development, Federal Highway 
Administration.
[FR Doc. 2019-07178 Filed 4-17-19; 8:45 am]